PROPOSED BUDGETS

H

        Back to Project Plan

Component/Task

Effort

(Person Hours)

Quantity

Unit Price ($)

Total Cost ($)

Signal Generator

40

2

35.00

70.00

Signal Receiver

35

2

20.00

40.00

Direction Sensor

50

1

25.00

25.00

Water Sensor

25

1

5.00

5.00

Micro-Controller

60

1

10.00

10.00

LCD Display

35

1

20.00

20.00

Speaker

-

1

5.00

5.00

Battery

-

3

3.33

10.00

Class Time

90

-

                      -

                    -

Miscellaneous*

100

-

15.00

15.00

TOTAL

435

-

-

200.00

*  Miscellaneous includes research, web page updating, project poster, design review, oral presentation, and final report. However, financial cost ($) only includes project poster and final report.

 

HUMAN EFFORT BUDGETS

Each member of the team will spend approximately 5 hours per week that includes class and group meetings, research, implementation, and design. As a result, each person will have to devote a total of 145 hours for two semesters (30 weeks). In the first semester for example, each member would probably need to spend at least 80 hours to design the hardware and software parts of the project where the rest of the hours are devoted to research, project poster, design review, and oral presentation.

 

        Back to Project Plan